When a Thai road cracks, who pays to fix it?
A Mukdahan road repair and a published Roi Et contract show when Thai public authorities can make contractors pay to fix defects after handover.
A reinforced-concrete road in Ban Kho, Mukdahan, had cracked in several places. The provincial good-governance committee called for a second inspection. The district chief reported that a working group visited the road with the contractor and recommended a cement-based repair. The contractor carried it out at no charge to the authority because the work was still under warranty. That is the outcome recorded in the committee’s 2020 annual report. The report leaves open how much the contractor spent and when notices were sent. Provincial good-governance committees’ 2020 annual report, p. 23
For a resident reporting a crack, the obvious question is when someone will come to fix it. The authority also has to work out whether the failure falls within the original contract and whether it can recover the cost if it sends someone else. Those answers depend on the handover date, what the inspection finds and what the contract says.
What survives handover
The Ministry of Finance’s public procurement regulation gives the head of the unit responsible for the asset, or a delegate, the job of maintaining and checking it during the contractual defect period. It assigns that job to the chief procurement officer where there is no custodial unit or several units share custody. If a defect appears within the warranty period, the responsible officer must report it promptly so the head of the agency can notify the contractor to repair it and notify the guarantor where there is one. Procurement regulation, clause 184 · Clause 185
The contract gives those duties dates and terms. The Roi Et Provincial Administrative Organisation published an agreement dated April 2024 for a 1.7-kilometre asphalt road from Ban Khwao Noi to Ban Sang. Clause 8 covers damage caused by the contractor’s unsuitable materials, poor workmanship or work below professional standards. The two-year period starts the day after handover. The contract gives the authority a remedy if the contractor fails to act within 15 days starting the day after receiving written notice, or fails to complete the correction within the time set by the authority. Roi Et road contract, April 2024, clauses 1 and 8
A crack can appear inside those two years for several reasons. Water can reach the road base. Traffic can impose loads the road was never designed to carry. The surface or the layers underneath it can also fall short of the design. In a contract worded like Roi Et’s, the practical question is whether the inspection ties the damage to the contractor’s work. The age of the crack helps establish the timing. Working out what caused it takes other evidence, such as the specification and the condition of the materials and layers. Federal Highway Administration’s pavement engineering manual, chapter 1 · Roi Et road contract, clause 8
When the authority can send the bill back
The Roi Et contract allows the authority to repair a covered defect itself or hire someone else at the original contractor’s expense if the contractor misses the contractual deadlines. It also allows the authority to intervene when an urgent repair cannot wait for the contractor. If the contractor fails to reimburse the costs or damages claimed under the contract, the authority can enforce the performance security. Clause 3 records a ฿289,850 bank guarantee, equal to 5 per cent of that contract’s price. The amount is the face value of the security. An actual payment under it would have its own record. Roi Et road contract, clauses 3 and 8
An older procurement committee determination shows how the money would be accounted for. Nong Phayom municipality in Phichit asked about guarantees for three contracts, including two concrete roads. The committee said that, if the municipality followed the required steps and the contractor failed to remedy a covered defect under the contract, the municipality could call the guarantee. If the repair cost less than the security collected, it was to return the balance. If the repair cost more, it could seek the shortfall from the contractor. The determination describes the municipality’s options. The eventual costs and any money recovered would be in the municipality’s records. Procurement committee determination on the Nong Phayom contracts, pp. 2–3
The check before the guarantee goes back
The procurement committee’s Circular W117 calls for a further inspection before the contractual warranty ends. For a two-year term like Roi Et’s, that means checking in the final 30 days and reporting the result. If damage is found, the circular instructs the agency to notify the contractor promptly to repair it before the period ends and to inform any guarantor. Clause 170(2) generally requires the authority to return the security promptly and within 15 days, counted from the day after the contractor is released from its obligations. The 2025 guidance on returning security still refers agencies to the W117 check. Circular W117, points 2–3 · Procurement regulation, clauses 170 and 186 · 2025 guidance, Circular W327
In Bang Phra, Chonburi, inspectors visited a road nearly seven years after its warranty had expired. The provincial office of the National Anti-Corruption Commission inspected a potholed crushed-stone road there in November 2023. It recorded that the warranty had ended in December 2016 and asked the local authority to restore the road. Its report ends at that referral. Any repair order, spending or recovery would need to be checked against what the authority did next. Chonburi NACC inspection, November 2023
To follow the bill on a road near us, start with the authority that commissioned the work. Its contract and handover record establish the period and the terms. The inspection and notice show whether it treated the damage as a defect under the contract. The repair record and accounts tell us whether the contractor did the work, the authority paid for it or the money came back through a claim. A patch can tell us the road was fixed. The accounts tell us who paid.
Common misconceptions
“Every road job comes with exactly two years of cover.” The Roi Et agreement specifies two years. Check the contract and handover date for the road in question.
“A pothole inside the warranty period establishes contractor liability.” The period addresses timing. Under the Roi Et terms, the defect must also be attributable to the contractor’s materials or work.
“The bank guarantee is the repair budget.” The Roi Et authority can enforce it if the contractor fails to pay amounts due under the contract. The Phichit determination shows how the actual repair cost can differ from the security collected.
Common questions
- Can a Thai road contractor be made to repair a road after handover?
- Yes, if the damage falls within the contract's defects warranty. The applicable terms and handover date define the period. The authority has to inspect and notify the contractor and any guarantor under the procurement rules.
- Do all Thai road warranties last two years?
- The published Roi Et example specifies two years from the day after handover. Check the agreement for the particular job.
- What happens if the road contractor fails to fix a covered defect?
- Under the Roi Et terms, the authority can do the work or engage someone else at the original contractor's expense after the relevant deadline. The contract also provides for urgent work and enforcement of the security if reimbursement is due and unpaid.
- When does the authority return the contract guarantee?
- The procurement rules call for a check before the warranty expires. Clause 170(2) generally requires the authority to return the security promptly and no later than 15 days counted from the day after the contractor is released from its obligations.
- Who fixed the cracked road in Mukdahan?
- The provincial good-governance committee's 2020 annual report says the contractor completed the repair under warranty at no charge to the authority.